Colruyt continues its growths. There is need for a new logistics centre in Ollignies. TRBA carries out the plans, creating an easily accessible and efficiently structured site. Perfect for the punctual delivery to the Colruyt stores.

 

Challenge

TRBA installs 55,000 m² of platforms for the buildings. Furthermore, the 14,580 m² staff car park is paved in aggregates, 16,357 m² of reinforced concrete, 17,067 m² of fibre concrete and 8900 m² of asphalt. The road foundation a double soil stabilisation on site. A 500 m³ buffer basin of reinforced concrete to minimize the risk of flooding completes the project.

 

 

Client: 
Colim CVBA (Colruyt)
Project: 

The construction of the new logistics centre in Ollignies

Budget: 
6 840 000.00€